求翻譯:在D工序之前有兩條路徑,即B-D和B-C-D,由于兩條路徑都可以完成D工作,所以選工期短的那條路徑為關(guān)鍵路徑,B-D路徑的工期為40天,B-C-D路徑的工期為70天,所以B-D路徑為關(guān)鍵路徑。是什么意思?![]() ![]() 在D工序之前有兩條路徑,即B-D和B-C-D,由于兩條路徑都可以完成D工作,所以選工期短的那條路徑為關(guān)鍵路徑,B-D路徑的工期為40天,B-C-D路徑的工期為70天,所以B-D路徑為關(guān)鍵路徑。
問題補充: |
|
2013-05-23 12:21:38
There are two paths before in d process, namely bd and bcd, two paths can be done d, so choose a short duration of that path, critical path, the bd path duration of 40 days the bcd path duration for 70 days, bd path for the critical path.
|
|
2013-05-23 12:23:18
Before operations in D There are two paths, i.e. B - D and B - C - D, because the two paths are D work can be done, so check the short construction period that path to critical path, the path D B - duration of 40 days, B - C - D path for the period was 70 days, so B - D path to critical path.
|
|
2013-05-23 12:24:58
In front of D working procedure has two ways, namely B-D and B-C-D, because two ways both may complete the D work, therefore chooses the time limit for a project short that way is the essential way, the B-D way time limit for a project is 40 days, the B-C-D way time limit for a project is 70 days, t
|
|
2013-05-23 12:26:38
D process, there are two paths, namely B-D and B-C-D, because the d two paths can be completed, so the path of the selected duration shorter for key path, b-d path has a duration of 40 days, 70-day duration of the B-C-D path, so B-D the path to the critical path.
|
|
2013-05-23 12:28:18